State-owned Oil and Natural GasBSE -0.59 % Corp (ONGCBSE -0.59 %) may buy out gas utility GAIL India LtdBSE -5.09 % in its Dahej mega petrochemical project in Gujarat to take full control of the recently commissioned plant.
GAIL had in 2008 picked up 19 percent stake in ONGC Petro-additions Ltd (OPaL), which was then building the mega petrochemical complex at Dahej in Gujarat.
But the project, which started in 2006, faced major cost and time overruns, which forced GAILBSE -5.09 % to restrict its equity contribution to the original Rs 996.28 crore. This investment in the expanded project cost meant that the gas utility’s stake dropped first to 17 percent, then to 15.5 percent and now about 9 percent, sources privy to the development said.
“It doesn’t make any business sense to hold such a small percentage stake and it is best that ONGC buys out GAIL in the project,” they said.
The 1.1 million tonnes plant, which at the time of conception was projected to cost Rs 12,440 crore, got completed only last year for about Rs 30,000 crore.
After GAIL in 2008 agreed to pick up 19 percent stake in OPaL, the project cost was in 2010 was revised to Rs 19,535 crore. It was couple of years later further revised upwards to Rs 21,396 crore with December 2013 set as the commissioning date.
Consequently, it decided to make an equity contribution of Rs 996.28 crore towards the 17 percent stake, they said.
But when the project cost went up further to Rs 21,396 crore, the promoter’s equity contribution increased from Rs 5,860.5 crore to Rs 6,418.8 crore at 70:30 debt-equity ratio.
GAIL, sources said, is not inclined to make any additional equity contribution and has decided to cap its investment in OPaL at the capital it has already approved Rs 996.28 crore. This, in the revised project cost, fetched it only 15.5 percent stake.
Now that the project cost almost touched Rs 30,000 crore, that investment is equivalent to only about 9 percent stake.
Sources said GAIL would, however, continue to hold rights to market 38 percent of the polymer and other chemicals produced by OPaL even at the reduced equity stake.
ONGC has funded almost all of the enhanced project cost after GAIL as well as Gujarat State Petroleum Corp (GSPC), which was to originally hold 5 percent stake, did not make more equity contributions.
ONGC had attributed the increase in project cost primarily to additional cost of Phase-II captive power plant and increase in cost of building the Phase-I electricity generating unit.